Back to projects

Procurement and Installation of Transformer and Power Generating Set for Dr. Victor Olunloyo Monumental Park and Energy Storage Upgrade for LED Gantry

Completed Infrastructure
placeholder

Project Information

Location
Procurement and Installation of Transformer and Power Generating Set for Dr. Victor Olunloyo Monumental Park and Energy Storage Upgrade for LED Gantry
Distance
— km
Progress
100%
Contractor
Direct Intervention
Start
Apr 23, 2025
Est. Completion
Oct 23, 2025
Budget
₦224,781,750

Project Progress

Overall completion: 100%
Milestones
  • ● Procurement completed
  • ● Construction mobilized
  • ● Phase 1 deliverables met
100%
Complete
Past estimated end

Location Map

Quick info

Progress: 100%

Start: Apr 23, 2025

Est. End: Oct 23, 2025

Contractor: Direct Intervention