Back to projects

Approval of Variation Cost to the Provision of High Mast Floodlights at Interchanges along Senator Rashidi Ladoja Circular Road Bridges 1 and 6 and Onipepeye, Ibadan

Ongoing Infrastructure
placeholder

Project Information

Location
Approval of Variation Cost to the Provision of High Mast Floodlights at Interchanges along Senator Rashidi Ladoja Circular Road Bridges 1 and 6 and Onipepeye, Ibadan
Distance
— km
Progress
65%
Contractor
CU Phosco & Haven Energy Solution
Start
Feb 10, 2025
Est. Completion
Apr 14, 2025
Budget
₦4,789,876,105

Project Progress

Overall completion: 65%
Milestones
  • ● Procurement completed
  • ● Construction mobilized
  • ● Phase 1 deliverables met
65%
Complete
Past estimated end

Location Map

Quick info

Progress: 65%

Start: Feb 10, 2025

Est. End: Apr 14, 2025

Contractor: CU Phosco & Haven Energy Solution