Project Information
Location
Asphaltic Improvement of Some Selected Roads
Distance
10.83 km
Progress
100%
Contractor
Craneburg Const. Comp.
Start
Dec 15, 2023
Est. Completion
Aug 15, 2024
Budget
₦6,100,875,841
Project Progress
Overall completion: 100%
Milestones
- ● Procurement completed
- ● Construction mobilized
- ● Phase 1 deliverables met
100%
Complete
Past estimated end
Location Map
Quick info
Progress: 100%
Start: Dec 15, 2023
Est. End: Aug 15, 2024
Contractor: Craneburg Const. Comp.