Back to projects

Asphaltic Rehabilitation and Overlay of Road Network Within the Legacy Estate, Kolapo Ishola GRA, Ibadan

Ongoing Infrastructure
placeholder

Project Information

Location
Asphaltic Rehabilitation and Overlay of Road Network Within the Legacy Estate, Kolapo Ishola GRA, Ibadan
Distance
— km
Progress
0%
Contractor
N/A
Start
Aug 22, 2025
Est. Completion
Nov 22, 2025
Budget
₦598,885,617

Project Progress

Overall completion: 0%
Milestones
  • ● Procurement completed
  • ● Construction mobilized
  • ● Phase 1 deliverables met
0%
Complete
Past estimated end

Location Map

Quick info

Progress: 0%

Start: Aug 22, 2025

Est. End: Nov 22, 2025

Contractor: N/A