Project Information
Location
Award of Contract for the Expansion of Scope of work on the Asphaltic Improvement of some Selected Roads within Ibadan Metropolis (LOT2) Splash FM Junction - Arapaja Junction,Felele
Distance
0.5 km
Progress
20%
Contractor
RATCON Construction Company
Start
Feb 10, 2025
Est. Completion
Aug 10, 2025
Budget
₦8,651,493,590
Project Progress
Overall completion: 20%
Milestones
- ● Procurement completed
- ● Construction mobilized
- ● Phase 1 deliverables met
20%
Complete
Past estimated end
Location Map
Quick info
Progress: 20%
Start: Feb 10, 2025
Est. End: Aug 10, 2025
Contractor: RATCON Construction Company