Location
Asphaltic Improvement/ Rehabilitation of some Selected Roads In Ibadan Metropolis (Lot 1)
Distance
70.45 km
Progress
87%
Contractor
KOPEK Construction Limited
Start
Feb 27, 2025
Est. Completion
Aug 27, 2025
Budget
₦34,531,037,896
Project Progress
Overall completion: 87%
Milestones
- ● Procurement completed
- ● Construction mobilized
- ● Phase 1 deliverables met
87%
Complete
Past estimated end
Location Map
Quick info
Progress: 87%
Start: Feb 27, 2025
Est. End: Aug 27, 2025
Contractor: KOPEK Construction Limited