Reconstruction of Government Quarters 363 as Permanent Headquarters of Oyo State Rule of Law Enforcement Authority

Reconstruction of Government Quarters

Ongoing Infrastructure
placeholder

Project Information

Location
Reconstruction of Government Quarters 363 as Permanent Headquarters of Oyo State Rule of Law Enforcement Authority
Distance
— km
Progress
50%
Contractor
Messrs. BTS Venture Nigeria Limited
Start
May 16, 2025
Est. Completion
Nov 16, 2025
Budget
₦294,680,274

Reconstruction of Government Quarters

Project Progress

Overall completion: 50%
Milestones
  • ● Procurement completed
  • ● Construction mobilized
  • ● Phase 1 deliverables met
50%
Complete
Past estimated end

Location Map

Quick info

Progress: 50%

Start: May 16, 2025

Est. End: Nov 16, 2025

Contractor: Messrs. BTS Venture Nigeria Limited