Expansion of scope of work on the Senator Ladoja Circular Road LOT 2: Jagun - Ibd/Ife Interchange; Const. of Toll Plaza, Flyover, Underpass, Exit & Entry Points with Mini Toll-gate

Ongoing Infrastructure
placeholder

Project Information

Location
Expansion of scope of work on the Senator Ladoja Circular Road LOT 2: Jagun - Ibd/Ife Interchange; Const. of Toll Plaza, Flyover, Underpass, Exit & Entry Points with Mini Toll-gate
Distance
16.7 km
Progress
48%
Contractor
Kopek Const. Ltd
Start
Jul 12, 2023
Est. Completion
Sep 16, 2025
Budget
₦92,284,313,211

Project Progress

Overall completion: 48%
Milestones
  • ● Procurement completed
  • ● Construction mobilized
  • ● Phase 1 deliverables met
48%
Complete
Past estimated end

Location Map

Quick info

Progress: 48%

Start: Jul 12, 2023

Est. End: Sep 16, 2025

Contractor: Kopek Const. Ltd