Implementation of the Road Infrastructure Component of the 32.2km Section (Eastern Wing) of Senator Ladoja Circular Road Lot 1: Lag/Ibd Interchange-Jagun Craneburg Const.

Ongoing Infrastructure
placeholder

Project Information

Location
Implementation of the Road Infrastructure Component of the 32.2km Section (Eastern Wing) of Senator Ladoja Circular Road Lot 1: Lag/Ibd Interchange-Jagun Craneburg Const.
Distance
15.5 km
Progress
69%
Contractor
Craneburg Construction
Start
Jan 01, 2024
Est. Completion
Sep 01, 2025
Budget
₦56,884,801,698

Project Progress

Overall completion: 69%
Milestones
  • ● Procurement completed
  • ● Construction mobilized
  • ● Phase 1 deliverables met
69%
Complete
Past estimated end

Location Map

Quick info

Progress: 69%

Start: Jan 01, 2024

Est. End: Sep 01, 2025

Contractor: Craneburg Construction