Remodelling and Renovation of Governors Lodge and State Liaison Office

Ongoing Infrastructure
placeholder

Project Information

Location
Remodelling and Renovation of Governors Lodge and State Liaison Office
Distance
— km
Progress
31%
Contractor
Feyton Lanreolu Associates
Start
Apr 25, 2024
Est. Completion
Feb 13, 2025
Budget
₦332,134,999

Project Progress

Overall completion: 31%
Milestones
  • ● Procurement completed
  • ● Construction mobilized
  • ● Phase 1 deliverables met
31%
Complete
Past estimated end

Location Map

Quick info

Progress: 31%

Start: Apr 25, 2024

Est. End: Feb 13, 2025

Contractor: Feyton Lanreolu Associates