Location
Upgrade of Airside Infrastructure of Samuel Ladoke Akintola Airport, Alakia Ibadan
Distance
— km
Progress
58%
Contractor
Craneburg Construction Company
Start
Sep 20, 2024
Est. Completion
Sep 20, 2025
Budget
₦41,270,712,601
Project Progress
Overall completion: 58%
Milestones
- ● Procurement completed
- ● Construction mobilized
- ● Phase 1 deliverables met
58%
Complete
Past estimated end
Location Map
Quick info
Progress: 58%
Start: Sep 20, 2024
Est. End: Sep 20, 2025
Contractor: Craneburg Construction Company